A comprehensive project where modX designed and installed 23 modular buildings to support maintenance operations. The project showcased our capability to handle large-scale installations, providing robust facilities for workforce accommodation and operational support.

Location: Stanwell, Queensland
Completion Date: July 2023
Builder: modX

The Stanwell Power Station (SPS) Outage Village stands as a testament to the collaboration between Stanwell and local businesses under the Buy Local, Build Local initiative. This state-of-the-art facility was designed to provide a single location for various teams of specialists to collaborate during major maintenance projects like the SPS Unit 1 overhaul, fostering efficiency and coordination in operational matters.

Built by modX, the SPS Outage Village consists of 23 modular buildings fully equipped with power, water, and sewage connections. Completed in July 2023, the village now serves as the central hub for specialists, trades, engineering, and health, safety, and environment (HSE) teams working on critical outage programs.

Key Features

  • 23 Modular Buildings: Fully connected to essential utilities, offering versatile spaces for offices, lunchrooms, and amenities blocks
  • Efficient Collaboration: Designed to house multiple teams working together on large-scale maintenance projects
  • Central Hub: Replaces the need to transport temporary buildings, offering a long-term solution for Stanwell's operational needs

Stanwell’s commitment to local supply chains was evident throughout the project. Through close collaboration with Stanwell’s procurement, HSE specialists, and project managers, modX was able to expand its capabilities and meet the stringent regulatory requirements of the project. This partnership not only ensured the successful delivery of the SPS Outage Village but also empowered modX to grow, resulting in a 50% increase in employees and contractors.

The Stanwell Power Station Outage Village was completed on time and within budget, ready for the 2023 Unit 1 overhaul. The village now accommodates up to 500 workers during outages, providing essential facilities for the smooth execution of maintenance programs.

Paul Abbott, Director of modX, expressed pride in the project’s success:

"Designing and constructing a complex of this size within 12 months was a significant achievement. We are grateful for the support from Stanwell and for the opportunity to contribute to such a pivotal project."